Explore the projects, their defining features and the scope of the experience behind each entry.
Clean Fuel Project
Europe·2023
A refinery-related assignment in Europe reviewed through ICC arbitration in 2023. The work reconstructed the construction timeline from planned and actual records, providing a technical account of the sequence of delay on an industrial project.
“Clean Foil Project” as written in CV
Thailand·2020
A clean-fuel industrial project in Thailand delivered by an international EPC joint venture. The 2020 assignment examined individual time impacts across the works, linking construction events to changes in the overall delivery programme.
Clean Oil Facility
Kuwait·2019
An industrial clean-oil facility in Kuwait delivered under an engineering, procurement and construction arrangement. The 2019 engagement involved a team review of planned and actual construction progress and its implications for the delivery period.
Central processing facility: three oil trains
Iraq·2018
A central oil-processing facility in Iraq comprising three oil trains. The 2018 assignment examined progress across the EPC construction programme, assessing how the sequence of events affected the timing of the processing-facility works.
Central processing facility: civil works
Kuwait·2018
The civil-works package of a central processing facility in Kuwait. The review focused on the subcontracted construction scope, assessing its delivery history and providing the EPC contractor with a technical basis for commercial discussions.
Refinery: civil works for 81 tank-farm tanks
Saudi Arabia·2018
A refinery tank-farm civil-works package in Saudi Arabia covering 81 tanks. The 2018 review addressed the subcontractor’s delivery position and the time and cost issues associated with this extensive industrial package.
Ghaba North oil & gas pipeline
Oman·2017
An oil-and-gas pipeline construction project in the Ghaba North area of Oman. The 2017 assignment followed the programme through successive construction periods, reviewing how recorded events influenced the route works and the planned completion date.